Rochambeau Bridge Reconstruction Project
Reconstruction of I-84
bridges over the Housatonic River
bridges over the Housatonic River
Construction Alerts
Update: Week of 9/18/2023
This past week of September 11, we accomplished the following work: Continued final planting in the Southbury median Began wildflower establishment in the Newtown medians Continued grading & topsoiling in the Southbury median Continued to remove material off site from the laydown area Continued to monitor and control environmental Best…
Update: Week of September 11, 2023
This past week of September 4, we accomplished the following work: Began final planting in the Southbury median Continued to haul material to the temporary re-use stockpile area (TRSA) Continued grading & installation of topsoil in the Southbury median Continued to removal material off site from the laydown area Continued…
Update: Week of September 4, 2023
This past week of August 28, we accomplished the following work: Completed grading the water quality swale in Southbury Removed the topsoil screener off site Continued to haul material to the temporary re-use stockpile area (TRSA) Continued to remove material off site from the laydown area Continued to monitor and…
Update: Week of August 28, 2023
During the past week of Aug 21, we continued the following work: Installation of the water quality swale in Southbury Final plantings Screening of topsoil for use on site Movement of material to the temporary re-use stockpile area (TRSA) Removal of material off site from the laydown area Monitoring and…
Update: Week of August 14, 2023
This past week of August 7, we accomplished the following work: Completed rumble strips project-wide Continued to install the water quality swale in Southbury Continued final plantings Continued to screen topsoil for use on site Completed chain link fence project-wide Continued to monitor and control environmental BMPs No night work…
Update: Week of August 6, 2023
This past week of July 31, we accomplished the following work: Continued to restore access roads using material from the temporary re-use stockpile area (TRSA) Completed installation of metal beam rail project wide Continued to install the water quality swale in Southbury Continued final seeding and plantings Started final grooving…