Rochambeau Bridge Reconstruction Project

Reconstruction of I-84
bridges over the Housatonic River

Construction Alerts

Update: Week of July 26, 2021

Construction Alerts, News
Completed Work (Week of 7/19/2021) Poured concrete at the Pier 3 Cap (see first photo) and at Abutments 1 and 2 Began mobilizing and assembling a 300-ton crane (see second photo) which will be used for steel erection scheduled to begin in August. Upcoming Work (Week of 7/26/2021) Continue crane…

Update: Week of July 19, 2021

Construction Alerts, News
Completed Work (Week of 7/12/2021) Contractor took delivery of a new 300-ton crane in preparation for future steel erection Installed rebar and dowels at Abutment 1 Installed rebar and dowels at Pier 3 Installed Pier 2 bearings Poured concrete for Pier 3 stem Poured concrete for Abutment 1 beam seats…

Update: Week of July 12, 2021

Construction Alerts, News
No work is scheduled on the project for Saturday, July 10. Work accomplished during the week of July 5: Poured concrete at the stem section of Pier 3 Formed and placed rebar for Abutment 1 and 2 modifications Backfilled Abutment 1 During the week of July 12, we will: Form…
Menu