Rochambeau Bridge Reconstruction Project

Reconstruction of I-84
bridges over the Housatonic River

Construction Alerts

Update: Week of December 6, 2021

Construction Alerts, News
During this past week of November 29, we continued pouring parapet sections and began paving the approaches to the bridge on each side. The Contractor will be working both Saturday and Sunday, 12/4 & 12/5, this weekend.    During the week of December 6, 2021, anticipated work includes: Complete the…

Update: Week of November 29, 2021

Construction Alerts, News
This past week of 11/22/2021, work accomplished was as follows: Continued pouring parapet sections; Poured the Abutment 1 Approach Slab; Milled the asphalt pavement at the approaches to the bridge. We will be working Friday 11/26 and Saturday 11/27 without impacting traffic.  Upcoming work for the week of 11/29/2021 includes:…

Update: Week of November 22, 2021

Construction Alerts, News
During the past week of 11/14/21: We poured the final three deck sections of the I-84WB bridge deck; Placed “finger-type” expansion joints; Started pouring sections of bridge parapet. We will be working Saturday, 11/20. Upcoming work for the week of 11/22/2021 includes: Continue pouring parapet sections and placing finger joints;…
Menu