Rochambeau Bridge Reconstruction Project

Reconstruction of I-84
bridges over the Housatonic River

Construction Alerts

Update: Week of August 15, 2022

Construction Alerts, News
This past week of August 8, we: Completed removing structural steel from the project; Completed rebar placement for Pier 2 cap and poured concrete there; Chipped existing concrete at Pier 3 cap; Set formwork for the Pier 3 stem; Continued Abutment 2 modifications; and Placed temporary bents in river for…

Update: Week of August 7, 2022

Construction Alerts, News
This past week of August 1, 2022, we accomplished the following work: Continued to process steel and concrete removed from the old Eastbound bridge and trucking it off site Completed rebar placement for Pier 1 Cap and Pier 2 Stem Prefabricated rebar cage for Pier 2 Cap Poured concrete at…

Update: Week of August 1, 2022

Construction Alerts, News
Saturday 7/30/22 The Navigation Channel will be open. Contractor will be onsite continuing steel processing for load out. Contractor will be continuing Pier 2 concrete demolition. Contractor will prepare for the pier cap concrete pour for Pier 1. Completed Work (Week of 7/24/2022) Continued steel demolition of the eastbound bridge;…
Menu