Rochambeau Bridge Reconstruction Project
Reconstruction of I-84
bridges over the Housatonic River
bridges over the Housatonic River
Construction Alerts
Update: Week of June 27, 2022
This past week of June 20, the following work was accomplished: Continued the demolition of the Eastbound Bridge; removing deck and parapet between Piers 3 and 4 Formed and placed rebar for the Abutment 1 modifications On Saturday, June 25, the prime contractor will be working. However, the demolition sub-contractor…
Update: Week of June 20, 2022
This past week of June 13 work performed was as follows: Continued the demolition of the Eastbound Bridge; currently working removing deck and parapet between Piers 2 and 3. Formed and poured the backwall at Abutment 1 Worked on the modifications to Abutment 1 During the week of June 20,…
Update: Week of June 13, 2022
Completed Work this past Week of 6/06/2022: Continued concrete bridge deck demolition of the Eastbound bridge Continued drainage installation for the Newtown approach to the bridge Continued reinforcing installation for abutment backwall reconstruction on the Newtown side Saturday 6/11/22: The Navigation Channel is open. Contractor will be onsite relocating and…