Rochambeau Bridge Reconstruction Project

Reconstruction of I-84
bridges over the Housatonic River

Construction Alerts

Update: Week of November 29, 2021

Construction Alerts, News
This past week of 11/22/2021, work accomplished was as follows: Continued pouring parapet sections; Poured the Abutment 1 Approach Slab; Milled the asphalt pavement at the approaches to the bridge. We will be working Friday 11/26 and Saturday 11/27 without impacting traffic.  Upcoming work for the week of 11/29/2021 includes:…

Update: Week of November 22, 2021

Construction Alerts, News
During the past week of 11/14/21: We poured the final three deck sections of the I-84WB bridge deck; Placed “finger-type” expansion joints; Started pouring sections of bridge parapet. We will be working Saturday, 11/20. Upcoming work for the week of 11/22/2021 includes: Continue pouring parapet sections and placing finger joints;…

Update: Week of November 15, 2021

Construction Alerts, News
During the past week of 11/07/2021, work accomplished was as follows: Completed concrete deck pour #4 Completed concrete pour for approach slab at Southbury approach Formed and poured concrete wing wall parapets Performed concrete curing operations – ensuring concrete is covered with blankets, heating hoses, and cure water Continued installation…
Menu