This past week of August 28, we accomplished the following work:

  • Completed grading the water quality swale in Southbury
  • Removed the topsoil screener off site
  • Continued to haul material to the temporary re-use stockpile area (TRSA)
  • Continued to remove material off site from the laydown area
  • Continued to monitor and control environmental Best Management Practices (BMPs)

No work on Monday, September 4; enjoy the long weekend!

Next week of September 4, we plan to accomplish the following work:

  • Continue final grading in the Southbury median
  • Begin final plantings in Southbury
  • Continue to install topsoil in the Southbury median
  • Begin final grading at the TRSA
  • Continue to remove material off site from the laydown area
  • Continue to monitor and control environmental BMPs