This past week of August 28, we accomplished the following work:
- Completed grading the water quality swale in Southbury
- Removed the topsoil screener off site
- Continued to haul material to the temporary re-use stockpile area (TRSA)
- Continued to remove material off site from the laydown area
- Continued to monitor and control environmental Best Management Practices (BMPs)
No work on Monday, September 4; enjoy the long weekend!
Next week of September 4, we plan to accomplish the following work:
- Continue final grading in the Southbury median
- Begin final plantings in Southbury
- Continue to install topsoil in the Southbury median
- Begin final grading at the TRSA
- Continue to remove material off site from the laydown area
- Continue to monitor and control environmental BMPs