During the past week of September 20, work accomplished was as follows:
- Continued welding bridge bearings
- Began placement of overhang brackets and wooden deck formwork in exterior bays
- Started installation of galvanized steel stay-in-place deck formwork at Spans 3 and 4 at interior bays (between girders)
The week of September 27, will have similar work performed as we proceed along the length of the bridge placing deck formwork.
In addition, the contractor will be working Saturdays this week (9/25), and for the next several weeks, to take advantage of good weather to enable the bridge deck to be poured as early in the season as possible.