This past week of September 12, we accomplished the following work:

  • Completed the first two stages of structural steel erection
  • Continued to sound, chip and replace deteriorated-unsound concrete
  • Continued earthwork at Abutment 1 and Abutment 2
  • Continued to monitor and control dust and other environmental BMPs

The Contractor will be onsite working Saturday, September 17.

During the week of September 19, we will continue to:

  • Form and pour Abutment 1 finger joint drainage trough
  • Form and pour Abutment 2 finger joint drainage trough
  • Drill and install dowel reinforcing at Abutment 2
  • Receive delivery of structural steel members and crossframes
  • Install bearings