This past week of September 11, we accomplished the following work:
- Continued final planting in the Southbury median
- Began wildflower establishment in the Newtown medians
- Continued grading & topsoiling in the Southbury median
- Continued to remove material off site from the laydown area
- Continued to monitor and control environmental Best Management Practices (BMPs)
Next week of September 18, we plan to accomplished the following work:
- Continue final grading in the Southbury median
- Continue final plantings in Southbury
- Continue wildflower establishment in the Newtown medians
- Continue to install topsoil in the Southbury median
- Begin final grading at the temporary re-use stockpile area
- Continue to remove material off site from the laydown area
- Continue to monitor and control environmental BMPs