This past week of September 5, 2022, we accomplished the following work:
- Continued to take delivery of structural steel elements
- Concrete pour for Abutment 2 cheekwall
- Continued to sound, chip and replace deteriorated-unsound concrete
- Continued earthwork at Abutment 1 and Abutment 2
- Installed a portion of steel bridge bearings and load plates
- Post storm environmental restoration and cleanup
- Continued to monitor and control dust and other environmental BMPs
The Contractor will be onsite working Saturday, September 10.
During the week of September 12, 2022, we will continue to:
- Form and pour Abutment 1 finger joint drainage trough
- Form and pour Abutment 2 finger joint drainage trough
- Drill and install dowel reinforcing at Abutment 2
- Take delivery of structural steel members and crossframes
- Install bearings
Channel Update:
The Contractor has constructed a temporary bent for future steel erection in Span 2, which is over the navigation channel. The bent will be in place until late September. It will be well-lit and delineated so boaters can see it well in advance. A 75’ channel will be maintained between the bent and Pier 2.
Photos below:
- Steel girder erection
- Setting of the new girder (taken from Abutment 1 on the Newtown side, looking East, towards Southbury)
- Bearing load plate