This past week of October 24, we accomplished the following work:

  • Continued installation of stay-in-place deck forms and shear stud connectors
  • Began installation of deck reinforcement
  • Continued to rub and grind completed concrete surfaces
  • Poured concrete at Cleanout for Abutment 1 Finger Joint

Contractor will be working both Saturday and Sunday, 10/29-10/30

During the week of October 31, we will:

  • Continue installation of stay-in-place deck forms and shear stud connectors
  • Continue installation of deck reinforcement
  • Pour concrete for first section of deck starting at Abutment 2 (Southbury) side
  • Continued to rub and grind completed concrete surfaces