This past week of September 26, we accomplished the following work:
- Continued structural steel erection
- Began installation of temporary overhang brackets and edge forms
- Resumed drainage work on the Newtown approach
- Rub and grind completed concrete surfaces at Piers 2 & 3 and Abutments 1 & 2
- Continued earthwork behind Abutment 1 and Abutment 2
- Continued to monitor and control dust, and other environmental BMPs
The Contractor will not be working Saturday, October 1, due to pending weather.
During the week of October 3, 2022, we will:
- Begin to remove temporary steel erection supports
- Begin to weld hangars for stay-in-place deck formwork
- Continue to install temporary overhang brackets and edge formwork
- Continue to bolt and torque down steel connections
- Continue to form and pour Abutment 1 finger joint drainage trough
- Continue to form and pour Abutment 2 finger joint drainage trough
- Continue earthwork at Abutment 1 and Abutment 2
Channel Update:
The boating channel will be closed for remaining steel erection work over the water, see DEEP Boating Lake Zoar notice.