This past week of October 18, the following work was accomplished:

  • Continued forming and placing galvanized rebar on the WB bridge deck as we proceed from east to west (Southbury side to Newtown side).
  • Poured the first of seven (7) deck sections starting at Abutment 2.

During the week of October 25, we anticipate the following work:

  • Rebar placement and deck formwork will continue.
  • Pouring the second section of bridge deck (about mid-week).

The Contractor will continue to work Saturdays for the next several weeks to take advantage of good weather.