This past week of October 17, we accomplished the following work:

  • Continued installation of stay-in-place deck forms and shear stud connectors
  • Continued installation of temporary overhang brackets and edge forms
  • Continued to rub and grind completed concrete surfaces at Piers 2 & 3 and Abutments 1 & 2
  • Continued earthwork behind Abutment 1 and Abutment 2
  • Continued to monitor and control dust, and other environmental BMPs post-rain storms

The Contractor will be working Saturday, October 22.

During the week of October 24, we will:

  • Continue to install temporary overhang brackets and edge formwork
  • Continue to install stay-in-place deck forms and shear stud connectors
  • Begin installation of deck reinforcing bars
  • Form and pour concrete deck pour #1

Channel Update:

  • The boating channel is open.