This past week of September 25, we accomplished the following work:
- Completed grading in the Southbury median
- Continued to grade the temporary re-use stockpile area (TRSA)
- Completed topsoiling the Southbury median
- Completed plantings in the Southbury median
- Continued wildflower seeding in the Southbury median
- Continued to monitor and control environmental Best Management Practices (BMPs)
Next week of October 2, we plan to accomplished the following work:
- Continue final grading at the TRSA
- Continue final grading at the Fish Rock Road access road
- Begin punch list (night work)
- Continue final seeding at the Southbury median
- Continue final grading at the TRSA
- Continue to monitor and control environmental BMPs
As of Friday night, 9/29, we will be working nights Sunday and Monday next week, and then back to days.