This past week of October 10, 2022, we accomplished the following work:

  • Completed bolting and torque down of steel connections
  • Continued to remove temporary steel erection supports
  • Continued installation of temporary overhang brackets and edge forms
  • Continued to rub and grind completed concrete surfaces at Piers 2 & 3 and Abutments 1 & 2
  • Continued earthwork behind Abutment 1 and Abutment 2
  • Formed and poured concrete keeper blocks at pier and abutments
  • Began installation of stay-in-place deck forms and shear stud connectors
  • Continued to monitor and control dust, and other environmental BMPs post-rain storms

The Contractor will be working Saturday, October 15.

During the week of October 17, 2022, we will:

  • Remove temporary steel erection supports
  • Continue to install temporary overhang brackets and edge formwork
  • Continue to install stay-in-place deck forms and shear stud connectors
  • Continue earthwork at Abutment 1 and Abutment 2

Channel Update:

The boating channel on Lake Zoar is open.

Menu