This past week of October 31, 2022, we accomplished the following work:

  • Began to form the abutment wingwall extension walls
  • Continued installation of stay-in-place deck forms, foam filler, and shear stud connectors
  • Continued installation of temporary overhang brackets and edge forms
  • Continued concrete surface repair work for existing surfaces
    Continued to rub and grind completed concrete surfaces at Abutments & Piers
  • Continued earthwork behind Abutment 1 and Abutment 2
  • Completed concrete deck pour #1
  • Continued to monitor and control dust, and other environmental BMPs post-rain storms

The Contractor will be working both Saturday, November 5, and Sunday November 6.

During the week of November 7, 2022, we will continue to:

  • Install stay-in-place deck forms, foam filler, and shear stud connectors
  • Install deck reinforcing bars
  • Form, pour, and cure concrete decks
  • Form abutment wingwall extensions walls

Channel Update:

  • The boating channel is open.