During the past week of November 1, the following work was accomplished:
- Continued forming and placing galvanized rebar on the WB bridge deck as we proceed from east to west (Southbury side to Newtown side)
- Poured concrete at the third of seven deck sections
- Parapet formwork
- Approach slab grading
During the week of November 8, scheduled work is as follows:
- Continue rebar placement and deck formwork
- Pour the fourth section of bridge deck mid-to late-week
The Contractor will be working this Saturday, 11/6.