This past week of 11/22/2021, work accomplished was as follows:

  • Continued pouring parapet sections;
  • Poured the Abutment 1 Approach Slab;
  • Milled the asphalt pavement at the approaches to the bridge.

We will be working Friday 11/26 and Saturday 11/27 without impacting traffic. 

Upcoming work for the week of 11/29/2021 includes:

  • Continue to pour parapet sections;
  • Continue to place membrane waterproofing on the bridge deck;
  • Begin paving full depth sections on the bridge approaches.

Final course of pavement is scheduled to occur in early-mid December.