This past week of November 14, we accomplished the following work:

  • Completed and began curing of deck pour #2
  • Continued to form the abutment wingwall extension walls
  • Continued installation of parapet mounted multi-duct conduit
  • Continued installation of Westbound bridge scuppers
  • Continued to install galvanized deck reinforcing steel
  • Continued concrete surface repair work for existing surfaces
  • Continued to rub and grind completed concrete surfaces at Abutments & Piers
  • Continued to monitor and control dust, and other environmental BMPs post-rain storms

The Contractor will be working Saturday, November 19, and Sunday, November 20.

During the week of November 21, we will continue to:

  • Complete installation of deck reinforcing bars
  • Install bridge scuppers
  • Form, pour, and cure concrete decks – Deck Pours 3 & 4
  • Form abutment wingwall extensions walls

Channel Update: The boating channel is open.