During the past week of 11/07/2021, work accomplished was as follows:
- Completed concrete deck pour #4
- Completed concrete pour for approach slab at Southbury approach
- Formed and poured concrete wing wall parapets
- Performed concrete curing operations – ensuring concrete is covered with blankets, heating hoses, and cure water
- Continued installation of galvanized deck reinforcing bars
- Began installation of parapet reinforcing bars
- Set catch basin frames to grade
- Replaced damaged speed limit and construction signs
Planned work for Saturday, 11/13/2021:
- Continue installation of galvanized deck reinforcing bars
- Continue installation of galvanized parapet reinforcing bars
Upcoming work for the week of 11/15/2021:
- Continue installation of galvanized deck reinforcing bars
- Continue installation of parapet reinforcing bars
- Continue forming bridge parapets
- Concrete pour for Newtown approach slab
- Concrete pour for bridge parapets
- Concrete pours for remaining bridge deck sections
Photos below:
- Concrete approach slab pour, completed on 11/09/2021
- Sunrise as contractor prepares for deck pour #4
- Concrete deck pour #4, completed on 11/11/2021