During the past week of 11/07/2021, work accomplished was as follows:

  • Completed concrete deck pour #4
  • Completed concrete pour for approach slab at Southbury approach
  • Formed and poured concrete wing wall parapets
  • Performed concrete curing operations – ensuring concrete is covered with blankets, heating hoses, and cure water
  • Continued installation of galvanized deck reinforcing bars
  • Began installation of parapet reinforcing bars
  • Set catch basin frames to grade
  • Replaced damaged speed limit and construction signs

Planned work for Saturday, 11/13/2021:

  • Continue installation of galvanized deck reinforcing bars
  • Continue installation of galvanized parapet reinforcing bars

Upcoming work for the week of 11/15/2021:

  • Continue installation of galvanized deck reinforcing bars
  • Continue installation of parapet reinforcing bars
  • Continue forming bridge parapets
  • Concrete pour for Newtown approach slab
  • Concrete pour for bridge parapets
  • Concrete pours for remaining bridge deck sections

Photos below:

  1. Concrete approach slab pour, completed on 11/09/2021
  2. Sunrise as contractor prepares for deck pour #4
  3. Concrete deck pour #4, completed on 11/11/2021