This past week of November 7, we accomplished the following work:
- Began to form the abutment wingwall extension walls
- Began installation of parapet mounted multi-duct conduit
- Began installation of Westbound bridge scuppers
- Completed installation of stay-in-place deck forms, foam filler, and shear stud connectors
- Completed installation of temporary overhang brackets and edge forms
- Continued to install galvanized deck reinforcing steel
- Continued concrete surface repair work for existing surfaces
- Continued to rub and grind completed concrete surfaces at Abutments & Piers
- Continued to monitor and control dust, and other environmental BMPs post-rain storms
The Contractor will not be working Saturday due to weather, but crews will be working Sunday November 13.
During the week of November 14, we will continue to:
- Install deck reinforcing bars
- Install bridge scuppers
- Form, pour, and cure concrete decks – Deck Pours 2 & 3
- Form abutment wingwall extensions walls
- Install parapet mounted multi-duct conduit
Channel Update: The boating channel is open.