This past week of October 25, the following work was accomplished:
- Continued forming and placing galvanized rebar on the WB bridge deck as we proceed from east to west (Southbury side to Newtown side)
- Poured concrete at the second of seven deck sections
During the week of November 1, we anticipate the following work:
- Continue rebar placement and deck formwork
- Pour the third section of bridge deck mid-to late-week
The Contractor will not be working Saturday, 10/30 due to the expected inclement weather.