Last week (week of May 1), we accomplished the following work:

  • Completed EB milling
  • Began installing a rip-rap swale from Alpine Dr. to the Rochambeau Bridge
  • Continued to form and pour sidewalks Newtown & Southbury
  • Continued spot-repair on existing substructure concrete
  • Continued to install rip-rap for slope protection
  • Continued to rub and grind parapet concrete
  • Continued to monitor and control environmental BMPs

During the week of May 8, we will pave the Eastbound bridge and continue to:

  • Install rip-rap swale from Alpine Dr. to the Rochambeau Bridge
  • Form and pour sidewalks Newtown & Southbury
  • Perform spot-repair on existing substructure concrete
  • Install rip-rap for slope protection
  • Rub and grind parapet concrete
  • Monitor and control environmental BMPs

 

 