This past week of May 15, we accomplished the following work:
- Completed metal beam rail on the eastbound bridge
- Continued to restore access roads using material from the TRSA
- Continued to install protective fence across the eastbound bridge
- Continued to install rip-rap for slope protection
- Completed parapet concrete sealing and caulking
- Began asphaltic plug joints on the Center St. Bridge
- Continued to monitor and control environmental BMPs
During the week of May 22, we will:
- Complete asphaltic plug joints on the Center St bridge
- Continue to restore access roads using material from the TRSA
- Continue to install protective fence across the eastbound bridge
- Continue to install rip-rap for slope protection
- Begin line striping the eastbound bridge
- Continue to monitor and control environmental BMPs