This past week of May 15, we accomplished the following work:

  • Completed metal beam rail on the eastbound bridge
  • Continued to restore access roads using material from the TRSA
  • Continued to install protective fence across the eastbound bridge
  • Continued to install rip-rap for slope protection
  • Completed parapet concrete sealing and caulking
  • Began asphaltic plug joints on the Center St. Bridge
  • Continued to monitor and control environmental BMPs

During the week of May 22, we will:

  • Complete asphaltic plug joints on the Center St bridge
  • Continue to restore access roads using material from the TRSA
  • Continue to install protective fence across the eastbound bridge
  • Continue to install rip-rap for slope protection
  • Begin line striping the eastbound bridge
  • Continue to monitor and control environmental BMPs