This past week of April 24, we accomplished the following work:
- Continued to form and pour sidewalk on both ends of the I-84 EB bridge
- Continued to grade for the Sidewalk on the Newtown side of the I-84 EB bridge
- Continued to install rip-rap for slope protection
- Continued to rub and grind parapet concrete
- Completed full depth paving on both ends of the I-84 EB bridge
- Continued to monitor and control environmental BMPs
During the week of May 1, we will:
- Begin EB full project limit milling
- Begin installing a rip-rap swale from Alpine Dr. to the Rochambeau Bridge
- Continue to form and pour sidewalks Newtown & Southbury
- Continue spot repair on existing substructure concrete
- Continue to install rip-rap for slope protection
- Continue to rub and grind parapet concrete
- Continue to monitor and control environmental BMPs