This past week of April 24, we accomplished the following work:

  • Continued to form and pour sidewalk on both ends of the I-84 EB bridge
  • Continued to grade for the Sidewalk on the Newtown side of the I-84 EB bridge
  • Continued to install rip-rap for slope protection
  • Continued to rub and grind parapet concrete
  • Completed full depth paving on both ends of the I-84 EB bridge
  • Continued to monitor and control environmental BMPs

During the week of May 1, we will:

  • Begin EB full project limit milling
  • Begin installing a rip-rap swale from Alpine Dr. to the Rochambeau Bridge
  • Continue to form and pour sidewalks Newtown & Southbury
  • Continue spot repair on existing substructure concrete
  • Continue to install rip-rap for slope protection
  • Continue to rub and grind parapet concrete
  • Continue to monitor and control environmental BMPs