This past week of March 20, we accomplished the following work:

  • Completed installation of Abutment 2 finger joint assembly
  • Resumed drainage work for final highway stormwater collection
  • Continued the removal of the temporary work trestle on the Southbury side
  • Continued rubbing and grinding the bridge parapets
  • Continued the installation of rip-rap for slope protection
  • Continued existing substructure concrete spot repair
  • Continued to monitor and control environmental BMPs

The Contractor will have crews working this weekend, both Saturday and Sunday.

During the week of March 20, we will:

  • Begin bridge deck surface prep for application of the waterproof membrane
  • Begin preparation to form and pour, and restore the concrete sidewalk pedestrian path
  • Complete removal of the temporary trestle
  • Continue to install navigation lighting (red) on the I-84 EB bridge
  • Continue existing substructure concrete spot repair
  • Continue to install rip-rap for slope protection
  • Continue to rub and grind parapet concrete
  • Continue to monitor and control environmental BMPs

 

 

 

 