This past week of March 20, we accomplished the following work:
- Completed installation of Abutment 2 finger joint assembly
- Resumed drainage work for final highway stormwater collection
- Continued the removal of the temporary work trestle on the Southbury side
- Continued rubbing and grinding the bridge parapets
- Continued the installation of rip-rap for slope protection
- Continued existing substructure concrete spot repair
- Continued to monitor and control environmental BMPs
The Contractor will have crews working this weekend, both Saturday and Sunday.
During the week of March 20, we will:
- Begin bridge deck surface prep for application of the waterproof membrane
- Begin preparation to form and pour, and restore the concrete sidewalk pedestrian path
- Complete removal of the temporary trestle
- Continue to install navigation lighting (red) on the I-84 EB bridge
- Continue existing substructure concrete spot repair
- Continue to install rip-rap for slope protection
- Continue to rub and grind parapet concrete
- Continue to monitor and control environmental BMPs