This past week of March 21, we continued excavating and grading in the median for the Eastbound Crossover and rubbing the new parapet on the south side of the new Westbound Bridge.
Upcoming Work for the Week of March 27, 2022:
On Sunday night 3/27 (one night only) starting at 7:00 PM, the left lane of I-84 EB will be closed to allow for the relocation of temporary precast concrete barrier curb so that final grading of the crossovers at the tie-in points at each end can be constructed.
During the week (days), from 3/28, the following work is scheduled:
- The south side of the new Westbound bridge deck will be cleared and swept in preparation for placement of membrane waterpoofing the week of April 4.
- We will be placing processed aggregate base in the crossovers in preparation for paving the week of April 11.