This past week of May 31, work continued on the removal of bridge deck and girders in Spans 1 and 2.
No work is anticipated this weekend.
Next week, during the week of June 6, work will continue on the removal of superstructure as we proceed across the bridge from Newtown to Southbury.
The navigation channel will be opened to boating traffic by the end of the day today, Friday 6/3, and remain open for the weekend.
Photos below show the bridge deck partially removed and the removal of the steel girders.