This past week, the week of June 20, we poured concrete for the Pier Cap at Pier 2 and for modifications to the Abutment 2 footing. On Saturday, June 26, workers will remove and roughen concrete at the top of Pier 3 in preparation for modifications to the pier cap there.
The week of June 28, we will:
- Backfill the abutments
- At Pier 3: Place formwork, install rebar, and pour concrete