No work is anticipated on the project Saturday, June 19.
This past week of June 7, we continued on the Abutment 2 modifications and placed formwork and rebar at the pier cap at Pier 2. Pier 3 footing was backfilled and the cofferdam removed.
The week of June 21, we will pour concrete at Pier 2 and Abutment 2. Additional piles will be driven for temporary supports for steel erection (currently scheduled to begin in August).
Here is a time-lapse video a of rebar cage being flown into place.