This past week of June 13 work performed was as follows:

  • Continued the demolition of the Eastbound Bridge; currently working removing deck and parapet between Piers 2 and 3.
  • Formed and poured the backwall at Abutment 1
  • Worked on the modifications to Abutment 1

During the week of June 20, the same work (with the exclusion of the backwall) will continue.

Navigation Channel Update: The channel will be closed from 6/27 thru 7/8 for the removal of steel girders over the channel.  We anticipate opening the channel for the July 4 weekend.