This past week of June 13 work performed was as follows:
- Continued the demolition of the Eastbound Bridge; currently working removing deck and parapet between Piers 2 and 3.
- Formed and poured the backwall at Abutment 1
- Worked on the modifications to Abutment 1
During the week of June 20, the same work (with the exclusion of the backwall) will continue.
Navigation Channel Update: The channel will be closed from 6/27 thru 7/8 for the removal of steel girders over the channel. We anticipate opening the channel for the July 4 weekend.