Update: Week of June 19, 2023

  1. Home
  2. News
  3. Update: Week of June 19, 2023

This past week of June 12, we accomplished the following work:

  • Finished installation of protective fence across the Eastbound bridge
  • Continued to install rip-rap for slope protection under the Eastbound bridge
  • Continued to install Turf establishment along EB
  • Continued excavation in the medians on the Newtown and Southbury sides
  • Completed removal of the Site 1 & 2 access road block walls
  • Continued to monitor and control environmental BMPs

The Contractor will be working Sunday night, June 18 from 8:00 PM to 6:00 AM

During the week of June 23, we will continue to:

  • Shift precast barrier on I-84 WB
  • Restore access roads using material from the temporary re-use stockpile area (TRSA)
  • Install the water quality swale Southbury & Newtown
  • Install rip-rap for slope protection
  • Restore the medians on the Newtown and Southbury sides
  • Monitor and control environmental BMPs