Completed Work this past Week of 6/06/2022:
- Continued concrete bridge deck demolition of the Eastbound bridge
- Continued drainage installation for the Newtown approach to the bridge
- Continued reinforcing installation for abutment backwall reconstruction on the Newtown side
Saturday 6/11/22:
- The Navigation Channel is open.
- Contractor will be onsite relocating and unloading demolition barges.
Upcoming Work (Week of 06/13/2022):
- Continue concrete bridge deck demolition
- Pour concrete for the abutment top of backwall reconstruction
- Continue reinforcing steel installation
- Continue dust control operations
- Resume excavation at the Newtown abutment
Photos Below:
- Abutment reconstruction progress
- Bridge deck demo progress
- Bridge deck demo progress
- Removal of supporting structural steel elements
- Panorama photo of current bridge conditions