This past week of June 5, we accomplished the following work:

  • Milled, paved, and striped I-84 EB tie-ins
  • Opened EB I-84 in its final alignment over the eastbound bridge
  • Continued to install protective fence across the eastbound bridge
  • Continued to install rip-rap for slope protection under the eastbound bridge
  • Continued to install turf establishment along I-84 EB
  • Began excavation of the medians on the Newtown and Southbury sides
  • Began removal of the temporary barrier
  • Continued to monitor and control environmental BMPs

During the week of June 12, we will continue to:

  • Remove temporary barrier
  • Restore access roads using material from the TRSA
  • Install protective fence across the eastbound bridge
  • Install rip-rap for slope protection
  • Restore the medians on the Newtown and Southbury sides
  • Monitor and control environmental BMPs