This past week of July 23, we accomplished the following work:

  • Continued to restore access roads using material from the temporary re-use stockpile area TRSA
  • Completed the water quality swale in Newtown
  • Continued to install the water quality swale in Southbury
  • Began final seeding and plantings
  • Completed plug joints on the Center Street Bridge westbound
  • Continued to screen topsoil for use on site
  • Continue to monitor and control environmental Best Management Practices BMPs

Night work continuing Sunday, July 30 to Friday, August 4 from 6 PM to 6 AM.
Working days from Monday, July 31 to Friday, August 4.

Next week of July 30, we plan to accomplished the following work:

  • Continued to restore access roads using material from the TRSA
  • Continued to install the water quality swale in Southbury
  • Install final line striping westbound
  • Install metal beam rail eastbound & westbound
  • Complete shoulder paving eastbound
  • Continue to monitor and control environmental BMPs