This past week of July 23, we accomplished the following work:
- Continued to restore access roads using material from the temporary re-use stockpile area TRSA
- Completed the water quality swale in Newtown
- Continued to install the water quality swale in Southbury
- Began final seeding and plantings
- Completed plug joints on the Center Street Bridge westbound
- Continued to screen topsoil for use on site
- Continue to monitor and control environmental Best Management Practices BMPs
Night work continuing Sunday, July 30 to Friday, August 4 from 6 PM to 6 AM.
Working days from Monday, July 31 to Friday, August 4.
Next week of July 30, we plan to accomplished the following work:
- Continued to restore access roads using material from the TRSA
- Continued to install the water quality swale in Southbury
- Install final line striping westbound
- Install metal beam rail eastbound & westbound
- Complete shoulder paving eastbound
- Continue to monitor and control environmental BMPs