Completed Work (Week of 7/12/2021)

  • Contractor took delivery of a new 300-ton crane in preparation for future steel erection
  • Installed rebar and dowels at Abutment 1
  • Installed rebar and dowels at Pier 3
  • Installed Pier 2 bearings
  • Poured concrete for Pier 3 stem
  • Poured concrete for Abutment 1 beam seats and pedestals
  • Poured concrete for Abutment 2 beam seats and pedestals
  • Stripped formwork from Pier 2
  • Shoreline/environmental cleanup following Tropical Storm Elsa
  • Emergency pothole patching of I-84 travel lanes

Work Scheduled for Saturday, 7/17/2021

  • Form stage 2 of the beam seat and pedestals at Abutment 2

Upcoming Work (Week of 7/19/2021)

  • Complete installation of steel erection shoring tower at Trestle Finger Span 3
  • Concrete pour for Pier 3 pier cap
  • Concrete pour for Abutment 2 beam seats and pedestals
  • Form and pour drainage trough slab at Abutment 1
  • Concrete finishing
  • Set bearings at Pier 1
  • Load-out WSA material to disposal facility

Photos Below:

  • Concrete pour of Abutment 2 beam seats and pedestals
  • Lifting formwork for Pier 3 pier cap