Completed Work (Week of 7/12/2021)
- Contractor took delivery of a new 300-ton crane in preparation for future steel erection
- Installed rebar and dowels at Abutment 1
- Installed rebar and dowels at Pier 3
- Installed Pier 2 bearings
- Poured concrete for Pier 3 stem
- Poured concrete for Abutment 1 beam seats and pedestals
- Poured concrete for Abutment 2 beam seats and pedestals
- Stripped formwork from Pier 2
- Shoreline/environmental cleanup following Tropical Storm Elsa
- Emergency pothole patching of I-84 travel lanes
Work Scheduled for Saturday, 7/17/2021
- Form stage 2 of the beam seat and pedestals at Abutment 2
Upcoming Work (Week of 7/19/2021)
- Complete installation of steel erection shoring tower at Trestle Finger Span 3
- Concrete pour for Pier 3 pier cap
- Concrete pour for Abutment 2 beam seats and pedestals
- Form and pour drainage trough slab at Abutment 1
- Concrete finishing
- Set bearings at Pier 1
- Load-out WSA material to disposal facility
Photos Below:
- Concrete pour of Abutment 2 beam seats and pedestals
- Lifting formwork for Pier 3 pier cap