On Saturday, 7/16, there will be ongoing concrete removal at Pier 1.
Week of 7/11: Completed work this past week included Abutment 1 footing concrete pours and ongoing steel removal operations.
Week of 7/18: During the week of July 18, and looking ahead, the contractor will continue steel removal operations, and continue pier concrete chopping and removal, pre-tiring of pier cap reinforcing, and dust control.