No work is scheduled on the project for Saturday, July 10.
Work accomplished during the week of July 5:
- Poured concrete at the stem section of Pier 3
- Formed and placed rebar for Abutment 1 and 2 modifications
- Backfilled Abutment 1
During the week of July 12, we will:
- Form and place rebar for the Pier Cap at Pier 3
- Pour concrete for Abutment 1 and 2 modifications
- Backfill Abutment 2
- Mobilize a large crane in preparation for steel erection scheduled for August.