No work is scheduled on the project for Saturday, July 10.

Work accomplished during the week of July 5:

  • Poured concrete at the stem section of Pier 3
  • Formed and placed rebar for Abutment 1 and 2 modifications
  • Backfilled Abutment 1

During the week of July 12, we will:

  • Form and place rebar for the Pier Cap at Pier 3
  • Pour concrete for Abutment 1 and 2 modifications
  • Backfill Abutment 2
  • Mobilize a large crane in preparation for steel erection scheduled for August.