Saturday, 7/9/2022

The Navigation Channel will be open.

The Contractor will be onsite:

  • Relocating and unloading demolition barges
  • Breaking down Abutment 1 temporary steel support to relocate to Abutment 2
  • Continuing to drill and grout reinforcing at Abutment 1
  • Continuing concrete demolition at Pier 1
  • Continuing to monitor dust

Completed Work (Week of 7/02/2022)

  • Continued steel demolition of the eastbound bridge
  • Continued to drill and grout reinforcing for Abutment 1 footing
  • Continued water transportation and rescue operations in support of demolition crews
  • Removed safespan demolition shielding
  • Completed concrete deck removal and removal of concrete approach slab

Upcoming Work (Week of 7/11/2022)

  • Continue steel demolition of eastbound bridge
  • Assemble and install effective concrete formwork platforms at piers
  • Continue reinforcing steel installation
  • Begin Abutment 1 footing formwork
  • Perform pre-assembly of pier reinforcing steel cages

Construction photos from this past week:

  1. Eastbound bridge deck demolition progress
  2. Abutment reconstruction progress
  3. Eastbound bridge steel demo progress