This past week of January 23, we continued to:
- Install parapet and safety curb reinforcing steel
- Form the abutment wingwall extension walls
- Form and pour the bridge parapet and safety curb
- Rub and grind poured parapet sections
- Remove overhang brackets
- Installation of permanent bridge drainage downspouts
- Monitor and control environmental BMPs
The Contractor will have crews working this Saturday, January 28.
During the week of January 30, we will continue to:
- Install parapet and safety curb reinforcing steel
- Form and pour the bridge parapet and safety curb
- Rub and grind completed parapet sections
- Remove overhang brackets
- Install permanent bridge drainage downspouts
- Monitor and control environmental BMPs