This past week of January 16, we continued to:

  • Install parapet and safety curb reinforcing steel
  • Form the abutment wingwall extension walls
  • Form and pour the bridge parapet and safety curb
  • Rub and grind poured parapet sections
  • Remove overhang brackets
  • Install permanent bridge drainage downspouts
  • Monitor and control environmental Best Management Practices (BMPs)

The Contractor will not be working this weekend.

During the week of January 23, we will continue to:

  • Install parapet and safety curb reinforcing steel
  • Form and pour the bridge parapet and safety curb
  • Rub and grind completed parapet sections
  • Remove overhang brackets
  • Install permanent bridge drainage downspouts
  • Monitor and control environmental BMPs