This past week of January 16, we continued to:
- Install parapet and safety curb reinforcing steel
- Form the abutment wingwall extension walls
- Form and pour the bridge parapet and safety curb
- Rub and grind poured parapet sections
- Remove overhang brackets
- Install permanent bridge drainage downspouts
- Monitor and control environmental Best Management Practices (BMPs)
The Contractor will not be working this weekend.
During the week of January 23, we will continue to:
- Install parapet and safety curb reinforcing steel
- Form and pour the bridge parapet and safety curb
- Rub and grind completed parapet sections
- Remove overhang brackets
- Install permanent bridge drainage downspouts
- Monitor and control environmental BMPs