This past week of January 10, we continued forming sections of parapet on the south side of the westbound bridge and started removing asphalt from the now abandoned westbound crossover in the median on the Southbury side.
During the week of January 17, we will continue working on that parapet and continue removing asphalt from the crossover. We will also remove and stockpile processed aggregate base from westbound crossover, which will be used for construction of the eastbound crossover.
Photos below:
- Facing west, traffic crosses the new westbound bridge
- Asphalt removal of the abandoned westbound crossover