During the week of 1/3/2022, we switched westbound (WB) traffic across the new WB Bridge. This will enable the construction of median crossovers during the winter months in preparation for the next stage of construction, which is the demolition and rehabilitation of the eastbound (EB) bridge.
I-84 EB traffic will remain in its current alignment until Spring 2022, when traffic will be shifted onto half of the WB roadway and across half of the new WB bridge using those crossovers. Bidirectional traffic will be separated by precast concrete barrier curb. This will clear traffic from the EB bridge and enable its reconstruction.
During the week of 1/10/22, we will continue work on the south parapet of the WB bridge and begin excavation/removal of the existing crossovers that are no longer required.