This past week of January 30, we accomplished the following work:
- Completed the installation of parapet and safety curb reinforcing steel
- Completed concrete pours for the safety curb
- Continued to form and pour the concrete bridge parapet
- Continued to form the abutment wingwall extension walls
- Continued to remove overhang brackets
- Continued installation of permanent bridge drainage downspouts
- Continued to monitor and control environmental BMPs
The Contractor will not have crews working this weekend.
During the week of February 6, we will:
- Begin backfill and fine grading for the abutment approach slabs
- Continue to form and pour the concrete bridge parapet
- Continue to rub and grind completed parapet sections
- Continue to remove overhang brackets
- Continue to install permanent bridge drainage downspouts
- Resume installation of rip-rap for slope protection
- Continue to monitor and control environmental BMPs