This past week of 2/14, we completed pouring concrete on the parapet of the Westbound bridge.
Now all concrete for that bridge has been placed. Excavation, grading and drainage work took place for the Eastbound Crossovers needed for the next stage of construction.
During the week of 2/21, work on the Eastbound crossovers will continue.
Access Roads from each side down to the river bank/trestle will be modified to accommodate the work required for the Eastbound Bridge.