This past week of February 6, we accomplished the following work:
- Began backfill and fine grading for the abutment approach slabs
- Completed dampproofing of the below grade abutment concrete surfaces
- Continued curing of concrete bridge parapet
- Continued to form and pour the abutment wingwall extension walls
- Continued to remove overhang brackets
- Continued installation of permanent bridge drainage downspouts
- Continued to monitor and control environmental BMPs
The Contractor will not have crews working this weekend.
During the week of February 13, we will:
- Continue to backfill and fine grading for the abutment approach slabs
- Continue to rub and grind completed parapet sections
- Continue to remove overhang brackets
- Continue to install permanent bridge drainage downspouts
- Resume installation of rip-rap for slope protection
- Prepare for removal of temporary trestle operations
- Continue to monitor and control environmental BMPs