This past week of February 6, we accomplished the following work:

  • Began backfill and fine grading for the abutment approach slabs
  • Completed dampproofing of the below grade abutment concrete surfaces
  • Continued curing of concrete bridge parapet
  • Continued to form and pour the abutment wingwall extension walls
  • Continued to remove overhang brackets
  • Continued installation of permanent bridge drainage downspouts
  • Continued to monitor and control environmental BMPs

The Contractor will not have crews working this weekend.

During the week of February 13, we will:

  • Continue to backfill and fine grading for the abutment approach slabs
  • Continue to rub and grind completed parapet sections
  • Continue to remove overhang brackets
  • Continue to install permanent bridge drainage downspouts
  • Resume installation of rip-rap for slope protection
  • Prepare for removal of temporary trestle operations
  • Continue to monitor and control environmental BMPs