Completed Work (Week of 12/12/2021)

  • Contractor resumed forming of concrete parapets for Westbound left shoulder.
  • Contractor began to seal and finish Westbound right shoulder concrete parapets.
  • Contractor began releasing and removing overhang brackets.
  • Subcontractor continue to install reinforcing steel bars for parapets.
  • Subcontractor completed Westbound line striping for future WB traffic shift.
  • Contractor mobilized and began installing temporary precast concrete barrier for future WB traffic shift.

No work is scheduled for this Saturday (12/18/21).

Upcoming Work (Week of 12/19/2021)

  • Contractor will continue installing temporary precast concrete barrier for future WB traffic shift.
  • Reinforcing subcontractor will continue installing parapet reinforcing steel bars.
  • Guiderail subcontractor will be onsite installing metal beam rail for future Westbound traffic shift.
  • Contractor will continue releasing and removing overhang brackets.
  • Contractor will continue to seal and finish Westbound right shoulder concrete parapets.

Photos below:

  1. Completed WB Right Shoulder parapet
  2. Aerial image of completed WB deck for upcoming WB Traffic Shift
  3. Contractor finishing concrete parapet