Completed Work (Week of 12/12/2021)
- Contractor resumed forming of concrete parapets for Westbound left shoulder.
- Contractor began to seal and finish Westbound right shoulder concrete parapets.
- Contractor began releasing and removing overhang brackets.
- Subcontractor continue to install reinforcing steel bars for parapets.
- Subcontractor completed Westbound line striping for future WB traffic shift.
- Contractor mobilized and began installing temporary precast concrete barrier for future WB traffic shift.
No work is scheduled for this Saturday (12/18/21).
Upcoming Work (Week of 12/19/2021)
- Contractor will continue installing temporary precast concrete barrier for future WB traffic shift.
- Reinforcing subcontractor will continue installing parapet reinforcing steel bars.
- Guiderail subcontractor will be onsite installing metal beam rail for future Westbound traffic shift.
- Contractor will continue releasing and removing overhang brackets.
- Contractor will continue to seal and finish Westbound right shoulder concrete parapets.
Photos below:
- Completed WB Right Shoulder parapet
- Aerial image of completed WB deck for upcoming WB Traffic Shift
- Contractor finishing concrete parapet