This past week of July 31, we accomplished the following work:

  • Continued to restore access roads using material from the temporary re-use stockpile area (TRSA)
  • Completed installation of metal beam rail project wide
  • Continued to install the water quality swale in Southbury
  • Continued final seeding and plantings
  • Started final grooving and line striping eastbound and westbound
  • Competed paving eastbound
  • Continued to screen topsoil for use on site
  • Continue to monitor and control environmental Best Management Practices (BMPs)

Night work continuing Sunday, August 6 to Friday, August 11 from 6 PM to 6 AM
Working days from Monday, August 7 to Friday, August 11

Next week of Aug 7, we plan to accomplished the following work:

  • Continue to restore access roads using material from the TRSA
  • Continue to install the water quality swale in Southbury
  • Continue final seeding and plantings
  • Complete final line striping eastbound and westbound
  • Complete rumble strips eastbound
  • Load out temporary barrier off site
  • Continue to monitor and control environmental BMPs