This past week of July 31, we accomplished the following work:
- Continued to restore access roads using material from the temporary re-use stockpile area (TRSA)
- Completed installation of metal beam rail project wide
- Continued to install the water quality swale in Southbury
- Continued final seeding and plantings
- Started final grooving and line striping eastbound and westbound
- Competed paving eastbound
- Continued to screen topsoil for use on site
- Continue to monitor and control environmental Best Management Practices (BMPs)
Night work continuing Sunday, August 6 to Friday, August 11 from 6 PM to 6 AM
Working days from Monday, August 7 to Friday, August 11
Next week of Aug 7, we plan to accomplished the following work:
- Continue to restore access roads using material from the TRSA
- Continue to install the water quality swale in Southbury
- Continue final seeding and plantings
- Complete final line striping eastbound and westbound
- Complete rumble strips eastbound
- Load out temporary barrier off site
- Continue to monitor and control environmental BMPs