This past week of August 1, 2022, we accomplished the following work:

  • Continued to process steel and concrete removed from the old Eastbound bridge and trucking it off site
  • Completed rebar placement for Pier 1 Cap and Pier 2 Stem
  • Prefabricated rebar cage for Pier 2 Cap
  • Poured concrete at the Pier 1 Cap and Pier 2 stem
  • Set formwork for the Pier 2 Cap
  • Chipped existing concrete at Pier 3 Cap
  • Began Abutment 2 modifications
  • Begin placing temporary bents in river for steel erection

The Contractor will be working Saturday, August 6.

During the week of August 7, 2022, we will:

  • Continue to process steel and concrete removed from the old Eastbound bridge
  • Set rebar cage and pour concrete at Pier 2 Cap
  • Complete chipping existing concrete at Pier 3 Cap
  • Possibly set formwork for Pier 3 Cap
  • Prefabricate rebar cage for Pier 3 Cap
  • Continue Abutment 2 modifications
  • Drive pile in river for temporary bents for steel erection

Channel Update:

The Contractor is currently constructing a temporary bent for steel erection in Span 2, which is over the navigation channel. The bent will be in place until late September. It will be well-lit and delineated so boaters can see it well in advance. A 75’ channel will be maintained between the bent and Pier 2.