Work Completed During the Week of July 26, 2021 was as follows:

  • Completed the abutment stem pours
  • Emptied the Waste Stockpile Area by transporting the material excavated from Pier 3 to an approved disposal facility
  • Completed the Span 3 Temporary Shoring Tower for steel erection, which is scheduled to begin the week of August 8.

Work scheduled for the Week of August 2, 2021 is as follows:

  • Complete the assembly of the 300-ton crane
  • Continue work on abutment backwalls/cheekwalls
  • Set up access for the delivery/storage of steel girders
  • Begin to accept steel delivery on site, possibly by late next week.