This past week (the week of August 9, 2021), we began accepting delivery and erecting structural steel girders in Span 4 (between Pier 3 (the easternmost pier) and Abutment 2). We also began grading and placing stone slope protection in front of Abutments 1 and 2.
During the week of August 16, 2021, steel delivery and erection will continue, proceeding to the west. Slope work will continue and the trough wall slab at the finger joint of Abutment 1 will be formed and poured.