This past week of August 7, we accomplished the following work:
- Completed rumble strips project-wide
- Continued to install the water quality swale in Southbury
- Continued final plantings
- Continued to screen topsoil for use on site
- Completed chain link fence project-wide
- Continued to monitor and control environmental BMPs
No night work is anticipated during the week of August 14.
Next week of August 14, we plan to accomplished the following work:
- Continue to install the water quality swale in Southbury
- Continue final plantings
- Continue to screen topsoil for use on site
- Start punch list repairs
- Continue to monitor and control environmental BMPs