This past week of August 7, we accomplished the following work:

  • Completed rumble strips project-wide
  • Continued to install the water quality swale in Southbury
  • Continued final plantings
  • Continued to screen topsoil for use on site
  • Completed chain link fence project-wide
  • Continued to monitor and control environmental BMPs

No night work is anticipated during the week of August 14.

Next week of August 14, we plan to accomplished the following work:

  • Continue to install the water quality swale in Southbury
  • Continue final plantings
  • Continue to screen topsoil for use on site
  • Start punch list repairs
  • Continue to monitor and control environmental BMPs