This past week of April 17, we accomplished the following work:

  • Completed forming and pouring the EB concrete barrier wall
  • Continued existing substructure concrete spot repair
  • Continued to install rip-rap for slope protection
  • Continued to rub and grind parapet concrete
  • Completed full-depth reconstruction of the roadway on EB Southbury side
  • Continued to monitor and control environmental BMPs

The Contractor will be working Saturday, April 22.

During the week of April 24, we will:

  • Begin to grade and form the EB sidewalk
  • Begin Paving EB full depth areas
  • Begin EB full project limit milling
  • Continue existing substructure concrete spot repair
  • Continue to install rip-rap for slope protection
  • Continue to rub and grind parapet concrete
  • Continue to monitor and control environmental BMPs