This past week of April 17, we accomplished the following work:
- Completed forming and pouring the EB concrete barrier wall
- Continued existing substructure concrete spot repair
- Continued to install rip-rap for slope protection
- Continued to rub and grind parapet concrete
- Completed full-depth reconstruction of the roadway on EB Southbury side
- Continued to monitor and control environmental BMPs
The Contractor will be working Saturday, April 22.
During the week of April 24, we will:
- Begin to grade and form the EB sidewalk
- Begin Paving EB full depth areas
- Begin EB full project limit milling
- Continue existing substructure concrete spot repair
- Continue to install rip-rap for slope protection
- Continue to rub and grind parapet concrete
- Continue to monitor and control environmental BMPs